BAKU TBLISI CEYHAN EXPORT PIPELINE

SITE: AZERBAIJAN AND GEORGIA
The Baku-Tbilisi-Ceyhan pipeline transports crude 1,760 km (1,094 miles) from the Azeri-Chirag-Guneshli oil field in the Caspian Sea to the Mediterranean Sea.
It passes through Baku, the capital of Azerbaijan; Tblisi, the capital of Georgia; and Ceyhan,
a port on the south-eastern Mediterranean coast of Turkey, hence its name.
It is the second longest oil pipeline in the world and one of the biggest engineering projects
of the decade.

EPC Contractor
Petrofac


Client
British Petroleum


SOLUTIONS DELIVERED
Engineering, manufacturing, testing and commissioning of PMCC type LV switchboards and Bus Ducts. Skema supplied switchboards for Pump stations PS-G2 and PS-G1 and for the intermediate Pigging 1P-A1.
The products supplied by Skema included:
• LV switchboards
(103 columns, 431 withdrawable units)
• DC panels
• Bus Ducts

Delivery time: 22 weeks.

“All in all the Skema service was very satisfactory.”